EstimateActivityDurationsistheprocessofe

免费题库2022-08-02  11

问题 EstimateActivityDurationsistheprocessofestimatingthenumberofworkperiodstocompleteindivitieswithestimatedresources.Thetoolsandtechnquesisnotincluding( ).A:expertjudgmentB:analogousestimatingC:requirementstraceabilitymatrixD:three-pointestimating

选项 A:expertjudgment
B:analogousestimating
C:requirementstraceabilitymatrix
D:three-pointestimating

答案 C

解析