If the task ______ by the end of this year is delayed, the company will be under punishment.
选项
A、being completed
B、is completed
C、to be completed
D、completed
答案
C
解析
时态题。本句话中complete的非谓语动词与the task是逻辑上的动宾关系,因此要用被动语态或过去分词形式。由于这是计划之中的事,因此用不定式。所以选项C 为正确答案。
转载请注明原文地址:http://tihaiku.com/zcyy/3811827.html
相关试题推荐
Forthesuccessoftheproject,thecompanyshould______themostoftheopport
Theannouncementoftheceasefirehasbeendelayedbecause[originaltext]Sen
WhyTonyBlairdelayedhisplanofannouncingtheelectioncampaign?[originalte
Morethanonce,Ibelieveeverybodyelseinourcompanywouldagreewithme,___
Ifthetask______bytheendofthisyearisdelayed,thecompanywillbeunder
Whyistheworld’slargestdrugcompanyembroiledinaglobalcontroversy?[br]
Lastweekthepresidentofthecompanyheldaparty,butpeoplethoughtitagre
Thecompanyhasemployedagirlwhois______atoperatingthecomputer.A、sufficie
Mr.Whiteworkswithachemicalsimport&exportcompany,buthe______forthein
Thefutureofthiscompanyis______:manyofitstalentedemployeesareflowing
随机试题
Whatisthemeetingabout?[originaltext]Goodmorning,boysandgirls.MayI
[originaltext]Whenquiteyoung,DanielWebsterdidnotalwaysobeytherule
AreFamiliesNecessary?Ashumanchildrenareunusual
Complainingaboutfaultygoodsorbadservicearenevereasy.【M1】
多元线性回归模型的拟和优度检验的方法有()。A.样本的可决系数B.施瓦茨准则
施工质量计划的编制主体是施工承包企业,施工企业应规定质量目标、方针、企业标准以及
小学科学《地球上的水》
请根据下来内容,回答101-104题。 表4—2某银行持有的各种货币的外汇敞口
某工程双代号时标网络计划如下图所示,其中③-④工作的自由时差和总时差分别为(
对于提升倾角较大的散装固体物料,其使用的输送设备有( )。A、振动输送机 B
最新回复
(
0
)