首页
登录
职称英语
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
游客
2024-03-11
50
管理
问题
Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、The municipal government kept changing hands.
B、The construction firm breached the contract.
C、Shortage of funding delayed its construction.
D、Problems of different kinds kept popping up.
答案
D
解析
目的原因题。讲座中提到,2012年,检查员发现消防安全系统不合格,之后又发现有90多米的电缆装错了,4,000扇门的序号不对,自动扶梯太短,登记柜台的数量也不够。由此可知,机场不断延期投入使用是因为层出不穷的问题。
转载请注明原文地址:http://tihaiku.com/zcyy/3525666.html
相关试题推荐
[originaltext]Whenwethinkofgames,thereareallkindsofthings.Maybeyou’
[originaltext]Whenwethinkofgames,thereareallkindsofthings.Maybeyou’
[originaltext]MyfellowSingaporeans:Whatwereyourmostmemorablemoments
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
随机试题
Everypersonplanstorunofftosometropicalisle,butfewdo.Reallife,
[originaltext]W:Iwanttobookapackagetour.I’dliketostopoverfivedaysi
行政复议制度也是我国的一项很重要的法律监督制度。这种监督属于A.权力监督 B.
用25兆赫硫酸锂晶片制的探头最适宜采用()探伤A.纵波接触法 B.水浸探伤法
用于桥涵工程的某砂筛分结果如下表所示:回答有关细度模数的计算方法和含义,砂粗细程
下列不属于胎盘早剥的症状是A.血性羊水 B.耻骨联合上闻及吹风样杂音 C.腹
在药物代谢动力学主要参数中,反映体内药物清除快慢的参数为( )。A.F B.
手阳明大肠经一般不治疗A.前头病 B.口鼻病 C.齿病 D.胸部病
甲以自己的名义,用家庭共有财产捐资设立以资助治疗麻风病为目的的基金会法人,由乙任
男,74岁,突发剧烈心前区疼痛,胸闷,气憋,心界向左扩大,心尖区Ⅲ级吹风样收缩期
最新回复
(
0
)