首页
登录
职称英语
As the windiest country in Europe, the United Kingdom’s wind power potential
As the windiest country in Europe, the United Kingdom’s wind power potential
游客
2023-10-14
44
管理
问题
As the windiest country in Europe, the United Kingdom’s wind power potential is larger than the rest of Europe put together. Half of this resource is in Scotland. The UK’s government has promised to generate 10% of their electricity using renewable resources. Wind power is seen to be the answer to doing this. The UK has issued wind farm licences to produce as much electricity as about six nuclear power stations. This policy has found favour with the public who support the search for cleaner energy sources.
Until 1989, Denmark was the only European state that had installed wind turbines for generating electricity. After 1989, other European countries followed suit developing support mechanisms for developing renewable energy and particularly wind power. Since 1994 the remaining European countries have also really started to support wind power station installation. Countries offer different levels of support. Some governments have paid companies premiums to maintain their competitive edge while others have given investment subsidies to foster the development of technology. Tax incentives have also been offered.
Nature provides us with indications for the best sites for wind turbine installation. Wind force and direction can be observed by leaning trees. This can most frequently be seen in open countryside and areas near coastlines and it is here, particularly in elevated spots clear of trees or buildings which obstruct the current of air, that wind farms have mostly been erected. Massive wind turbines, twice the size of conventional turbines, are also being developed for use offshore, as it is there that the strongest and most constant winds are found.
Believing that wind energy has no disadvantages is easy--it is clean, efficient and comparatively inexpensive and it creates no pollutants or emissions during operations. The electricity generated in the first 6 to 9 months of operation by a typical wind turbine will usually meet its manufacturing costs. However, wind farms are frequently regarded as a type of visual pollution because of their common locations on hilltops. It is inescapable that sites with the most wind are usually the most beautiful, and because they are built in wild, remote and untouched settings their impact is all the more noticeable. This is one of the most controversial questions when deciding on wind farm locations. Thus the setting of wind farms ought to be done with the greatest sensitivity. When turbines are due for decommission, the entire structure can be wholly recycled or removed and the cost of total site restoration can usually be completely met by the scrap value.
Wind turbines blades are made of glass fibre or wood epoxy and they can be of a diameter of 30 to 60 metres. The blades of the wind turbine generator are turned by the wind. The blades are joined to the hub that is in turn connected to the gear shaft. When the wind blows, the blades and hub turn the shaft that revolves within the generator; that then produces electricity. The power created is dependent on the blade size and the swept area. The speed of the wind and its availability are also key variables to be considered. The electricity is then moved to either the grid for regional use or to supply power to a stand-alone facility.
European operational capability was 2,500 megawatts in total by the end of 1995. By the end of 1996 it had increased to 3,400 MW and at the end of 1997 to 4,600 MW. There were steady increases in growth (40% per annum) over the following 6 years and the forecast is that this growth rate will persist. This is in contrast to practically zero growth in traditional fossil fuel energy production. Nonetheless, even at existing production levels, only 2% of potential energy is being exploited. In due course therefore wind farms may well satisfy 20% of total European power requirements. The European country with the most operational capacity is Germany. This is mostly down to the level of support given to wind power by Germany’s government. It has also been helped by recent innovation in the field of turbine development. [br] During the decommissioning of turbines, the cost of total site restoration can usually ______ the scrap value.
选项
答案
be completely met by
解析
(第四段最后一句提到When turbines are due for decommission, …the cost of total site restoration can usually be completely met by the scrap value可知风力发电机报废时废料的价值完全够修复遗址用。)
转载请注明原文地址:http://tihaiku.com/zcyy/3095793.html
相关试题推荐
Accordingtorecentsurveys,72%ofallAmericansbelievethattheUnitedSt
Accordingtorecentsurveys,72%ofallAmericansbelievethattheUnitedSt
Accordingtorecentsurveys,72%ofallAmericansbelievethattheUnitedSt
Accordingtorecentsurveys,72%ofallAmericansbelievethattheUnitedSt
Accordingtorecentsurveys,72%ofallAmericansbelievethattheUnitedSt
ThelatestHumanDevelopmentReportfromtheUnitedNationsDevelopmentProg
ThelatestHumanDevelopmentReportfromtheUnitedNationsDevelopmentProg
ThelatestHumanDevelopmentReportfromtheUnitedNationsDevelopmentProg
ThelatestHumanDevelopmentReportfromtheUnitedNationsDevelopmentProg
ThelatestHumanDevelopmentReportfromtheUnitedNationsDevelopmentProg
随机试题
A.hungryB.cookC.buyD.fillE.againF.poorG.before[br]needingsth.to
[img]2016m1x/ct_etoeiclm_etoeiclzp_0001_20161116[/img][br][originaltext](A)A
劳务分包单位施工人员在50~200人的,应当配备1名专职安全生产管理人员()
如果某隧道工程的施工网络计划如图2-2所示。 图2-2 某隧道工程的施工网
下列选项中,不属于垂体瘤实验室检查范畴的是A.腺垂体功能检查:GH、PRL、AC
持续发热,脾大,粒细胞减少,骨髓培养伤寒杆菌阳性为A.伤寒带菌者 B.骨髓炎
某市规划建设的4个小区,分别位于直角梯形A.B.C.D.的4个顶点处(如图),A
与氨基苷类抗生素或多黏菌素合用时易致呼吸麻痹的药物是A、后马托品 B、新斯的明
素质教育就是要学生什么都学,什么都学好。
下列各项所得,按“工资、薪金所得”缴纳个人所得税的有( )。A.年终一次性奖金
最新回复
(
0
)