Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、The municipal government kept changing hands.
B、The construction firm breached the contract.
C、Shortage of funding delayed its construction.
D、Problems of different kinds kept popping up.
答案
D
解析
目的原因题。讲座中提到,2012年,检查员发现消防安全系统不合格,之后又发现有90多米的电缆装错了,4,000扇门的序号不对,自动扶梯太短,登记柜台的数量也不够。由此可知,机场不断延期投入使用是因为层出不穷的问题。
转载请注明原文地址:http://tihaiku.com/zcyy/2909416.html
相关试题推荐
[originaltext]TheHarvardStudyofAdultDevelopmentmaybethelongeststu
[originaltext]Manypeopledislikewalkingintothebank,standinginlongl
[originaltext]Manypeopledislikewalkingintothebank,standinginlongl
[originaltext]Yuppiesareyoungpeoplewhoearnalotofmoneyandlivein
[originaltext]M:Timetoeat!W:Coming.Oh,I’mstarving.Ohyuck!What’sthat
[originaltext]M:Timetoeat!W:Coming.Oh,I’mstarving.Ohyuck!What’sthat
[originaltext]M:Timetoeat!W:Coming.Oh,I’mstarving.Ohyuck!What’sthat
[originaltext]W:We’veallheardthesaying"Laughteristhebestmedicine"How
[originaltext]W:We’veallheardthesaying"Laughteristhebestmedicine"How
[originaltext]Asaresultofrisinguniversitycosts,manystudentsarefin
随机试题
Understandingtheculturalhabitsofanothernation,especially______containing
甲农机厂主要制造不同型号的拖拉机和农用三轮车。该厂的分厂有5个,制造环节较多
某公司可在招聘公告中明确要求女性应聘者三年内不准怀孕。()
最后的节目合成排练要在演出前舞台装台工作基本完成后方能进行,排练时间一般为1-3
关于钙制剂临床应用中的注意事项描述,错误的是()A:补钙应选用含钙量高、生物利
股票()是股票发行制度的重要组成部分,不仅直接影响有关参与各方的利益分配,也
2021年12月,某公司发生相关税费如下:增值税为30万元,消费税为20万元,城
根据《堤防和疏浚工程施工合同范本》,因监理人指示错误发生的费用和给承包人造成的损
城镇道路路基施工质量检验与验收的主控项目有()。A、压实度 B、弯沉值 C、
关于施工企业违法行为应承担法律责任的说法,正确的是()。A.允许他人以本企业名
最新回复
(
0
)