首页
登录
从业资格
You are a project manager for a small pr
You are a project manager for a small pr
题库
2022-08-02
94
问题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided
选项
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
答案
B
解析
你是一个小项目的项目经理,项目的预算是50万元,工期是6个星期。到今天为止,你花费了26万元,而预算应完的工作对应的值为28万元,根据你的计划进度,你应在此时花费30万,基于这些情况,你的项目极可能落后于进度。
正确选项B。
转载请注明原文地址:http://tihaiku.com/congyezige/2413506.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
以下不属于信息系统项目管理工具的是()。A.MicrosofiProject
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
在下图一的SNMP配置中,能够响应Manager2的getRequest请求的是
在下图的SNMP配置中,能够响应Manager2的getRequest请求的是(
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique
Theprojectworkbookisnotsomuchase
Theprojectworkbookisnotsomuchase
Aprojectisa[temporary]()ofunique,co
随机试题
Itisestimatedthatapproximately350,000managersareneededinChina.Wit
DatingDatingisthe【T1】______firststeptowardmarriage.Butdatingan
Accustomedthoughwearetospeakingofthefilmsmadebefore1927as"silent
导致Rh血型鉴定可能出现假阳性的原因有A:弱D型B:患者红细胞直接抗人球蛋白试
围绝经期综合征的主要临床表现为A:约半数以上的妇女会发生比较明显的症状 B:卵
上市公司的总经理可以再控股股东担任的职务有()。A:总经理B:董事长C:副总
有效声誉风险管理体系应重点强调的内容包括()。A.努力建设学习型组织,有能力在
资产安全性监管是监管机构对银行机构监管的重要内容.监管重点是银行机构风险的分布、
投资项目决策分析与评价的基本要求包括贯彻落实科学发展观、资料数据准确可靠和()
下列工作中,不属于施工项目目标动态控制程序中的工作是()。A.目标分解
最新回复
(
0
)