首页
登录
从业资格
During planning you sit down and estimat
During planning you sit down and estimat
题库
2022-08-02
78
问题
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario ( ) .A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate;should be the same as the customer's reqhired completion date
选项
A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate;should be the same as the customer's reqhired completion date
答案
B
解析
当你计划坐下来,估计每个任务所需的时间和总他们的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是
B选项:团队不需要创建估算,不需要用到网络图
转载请注明原文地址:http://tihaiku.com/congyezige/2412589.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
企业系统规划(BusinessSystemPlanning,BSP)的实现步
Workaroundsaredeterminedduringwhich
Onetoolthatisusefulduringbothanal
Duringplanningyousitdownandestimat
Duringtheinstallationofthegroove,t
Duringtheimplementationoftheproject
Duringtheinstallationofthegroove,th
()Estimatingcurrentprojectcostsbya
Duringtheimplementationoftheproject
随机试题
[originaltext]Gladtomeetyou.[/originaltext][originaltext]That’saniceknif
Chaucerboremarksof______andthusisregardedastheforerunnerofEnglishR
[originaltext]M:Oh,Mrs.Jones.CanItakethetestnow?Ijust...W:Excusem
关于桥梁施工中大体积混凝土施工,以下叙述错误的是()。A.大体积混凝土可分层、分
学习《装在套子里的人》,教师用披风、靴子、高帽、墨镜、口罩、耳套把自己捂得严严实
根据现行GSP的规定A.药学或相关专业的学历,或者具有药学专业技术职称B.主管药
共用题干 患儿,8岁。血液检查显示:Hb64g/L;Hct25%;RBC3.2
某公司从境外进口小轿车30辆,每辆小轿车货价15万元,运抵我国海关前发生的运输费
审核人力资源费用预算的基本要求不包括( )。A.最小化 B.合理性
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
最新回复
(
0
)