( ) is a document generated by the creating WBS process that support the WBS , which provides more detailed descriptions of the components in the WBS 。A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list
选项
A.The project charter
B.The project scope statement
C.The WBS dictionary
D.The activity list
答案
C
解析
转载请注明原文地址:http://tihaiku.com/congyezige/2301863.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Managingriskanddocumentingthemisve
()isadocumentgeneratedbythecreat
Managingriskanddocumentingthemisve
Managingriskanddocumentingthemisve
()theprocessofdetermining,document
()isadocumentgeneratedbythecreatin
()istheprocessofdocumenting,analy
Documentationofasoftwarepackageisn
()istheprocessofdocumenting.Anal
Documentationofasoftwarepackageisn
随机试题
AccordingtothepassageweknowinPortugal______.[br][originaltext]W
[originaltext]Agrowingbodyofuniversityresearchsuggeststhatgamingim
originattractcommontreatstrongMarmaladeisatypeofja
Themobilephoneisamagicdevicewidelyusedthesedays.Althoughithasb
属于肝硬化肝功能减退的临床表现是A.脾肿大 B.腹水 C.腹壁静脉曲张 D
施工项目经理的任务包括项目的行政管理和项目管理两个方面,其在项目管理方面的主要任
邓小平坚持马克思主义的思想路线,把“解放思想”和“实事求是”联系起来表述,更鲜明
A B C D 7026~7862 1023~2046 20472~
某饭店一项设备的账面原值为100000元,预计净残值率为5%,使用年限为5年,则
某项目部承建的雨水管道工程管线总长为1000m,采用直径为900mm的HDPE
最新回复
(
0
)