Several riskresponse strategies are avai
Several riskresponse strategies are avai
考试题库
2022-08-02
44
问题
Several riskresponse strategies are available. ()the risk simply gives another party responsibility for itsmanagement,it does not eliminate risk.A.AvoidingB.MitigatingC.AcceptingD.Transferring
选项
A.Avoiding
B.Mitigating
C.Accepting
D.Transferring
答案
D
解析
一些风险反应策略是可行的。转移风险仅仅给另一方负责管理,但它并不能消除风险。
转载请注明原文地址:http://tihaiku.com/congyezige/2301808.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Severalriskresponsestrategiesareava
Severalriskresponsestrategiesareavai
Severalriskresponsestrategiesareavai
Therearestrategiestypicallydealwith
Thestrategiesforhandlingriskcompris
Therearestrategiestypicallydealwith
Thestrategiesforhandlingriskcompris
随机试题
WhydoreadersofNewScientistcontinuetogetsteamedupaboutrace?Afterall
[originaltext]W:Oh,Jack,I’mgladIcalledyou.IwanttotellyouIhaveto
Francemightbedescribedasan’all-round’country,onethathasachievedr
三十六岁,GP。因停经41周,胎膜早破2日,阵发性腹痛6小时入院。宫口开大2cm
与补体相关的检测CIC的方法不包括A.Cq凝胶沉淀试验 B.Cq偏离试验 C
明确把“关爱学生”作为一条中小学教师职业道德行为规范的是( )。A.1984年
工作单位对人类行为的影响有()。A.为受众提供支持其固有立场、观点和行为的有关
爱牙日到学校进行口腔健康知识宣传属于哪种口腔健康教育方法A.大众传媒 B.社区
20×7年2月1日,甲公司与乙公司签订了一项总额为20000万元的固定造价合同,
对由于承包商的原因所导致的工期延误,监理工程师可采取的制约手段包括()。A.停止
最新回复
(
0
)