A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. which would appear on the chart ( ) .A.4 weeksB.5 weeksC.6 weeksD.7 weeks
选项
A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks
答案
B
解析
转载请注明原文地址:http://tihaiku.com/congyezige/2301738.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Toensuretheprojectteamprovidesthe
Projectmanagerbelievesthatmodifying
A( )isasoftwarethatprovidesametho
A()isasoftwarethatprovidesametho
Alinemanagerprovidesyouwiththreee
Aprojectmanagerbelievesthatmodifyin
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
Projectmanagerbelievesthatmodifying
()isthatitprovidesguidanceanddi
随机试题
NicolausCopernicus’sideaswerefar_________theageinwhichhelived.That
Theconceptofpersonalchoiceinrelationtohealthbehaviorsisanimportan
Mailbox-watchinginsupposedtosubsideforhigh-schoolseniorsaftertheyr
抗结核的一线药物有()A:对氨基水杨酸 B:卡那霉素 C:异烟肼 D:利
为保证热拌沥青混合料的施工质量,应检测的施工温度有()。A.沥青混合料的出厂温度
在高湿度环境中或长期处于水中的混凝土应优先选用( )水泥。 A、矿渣 B
价值工程活动的核心是()。A:收集情报 B:功能整理 C:功能定义 D:功
李华是一个十分聪明的学生,他的最大特点就是贪玩,学习不用功。每次考试他都有侥幸心
长时间来,支付宝都是线上支付最主要的方式,但由于其在线支付,和其他网络应用一样,
(2016年真题)根据《民法典》的规定,债务人或第三人有权处分的下列权利中,可以
最新回复
(
0
)