首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
最全题库
2022-08-02
76
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
选项
A.the project is a head of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
答案
B
解析
挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:(74)A.项目滞后B.项目超前C.项目超支D.成本有结余
转载请注明原文地址:http://tihaiku.com/congyezige/2299751.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ethernetisthecommonlyusedlocalarea
Earnedvaluemanagement(EVM)integrates
Earnedvaluemanagement(EvM)integrates
Aprojectmanagementtechniquethatisc
Ethernetisthecommonlyusedlocalarea
()isaprojectmangementtechniqueform
()isoneofthetoolsandtechniqueso
Earnedvaluemanagement(EVM)integrates
()isatechniqueforestimatingthedu
随机试题
中国民族管弦乐团Chinesenationalorchestra
辅文的作用之一是( )。A.有利于图书定价 B.有利于检索 C.有利于文图
根据《建筑起重机械安全监督管理规定》,建筑起重机械安装完毕后,()应当组织出租
男孩,12岁,胸背部疼痛1天,伴双下肢进行性无力,尿潴留。体检:双上肢肌力5级,
《彼得与狼》的曲作者是()A.肖斯塔科维奇 B.普罗科菲耶夫 C.斯特拉
根据《首次公开发行股票承销业务规范》,下列关于首次公开发行股票投资价值研究报告的
输气压力为1.6MPa燃气管道为( )燃气管道。 A、次高压A B、次高
中国药典(2010年版)规定检查盐酸吗啡中"其他生物碱"的方法为A.HPLC
()是使投资组合中债券的到期期限集中于收益率曲线的一点。A:两极策略B:子弹式
下列各项中,企业可以将特定债权转为股权的是()。A.上市公司依法发行的公司债券
最新回复
(
0
)