首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
最全题库
2022-08-02
62
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
选项
A.the project is a head of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
答案
B
解析
挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:(74)A.项目滞后B.项目超前C.项目超支D.成本有结余
转载请注明原文地址:http://tihaiku.com/congyezige/2299751.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ethernetisthecommonlyusedlocalarea
Earnedvaluemanagement(EVM)integrates
Earnedvaluemanagement(EvM)integrates
Aprojectmanagementtechniquethatisc
Ethernetisthecommonlyusedlocalarea
()isaprojectmangementtechniqueform
()isoneofthetoolsandtechniqueso
Earnedvaluemanagement(EVM)integrates
()isatechniqueforestimatingthedu
随机试题
Everygenerationhasitsemblematicboy’stoy.Onceuponatimetherewasthe
Forthispart,youareallowed30minutestowriteashortessayonthetopicSt
Thenormalhumandailycycleofactivityisofsome7-8hours’sleepalterna
“冲击波”病毒属于()类型的病毒,它利用Windows操作系统的()漏洞进行快速
共用题干 TheMostWonderfulIslandsThePalm
胆总管结石合并急性胆管炎时表现为A:腹痛 B:寒战 C:高热 D:黄疸
质量检验的主要功能之一是“鉴别”。所谓“鉴别”是指()。[2008年真题]
压缩压力不足可能造成A.松片 B.裂片 C.崩解迟缓 D.黏冲 E.片重
(2016年真题)下列管理措施中,可以缩短现金周转期的有()。A.加快制造和销
编制“银行存款余额调节表”时,应调整银行对账单余额的业务有()。A、企业已收,银
最新回复
(
0
)