首页
登录
从业资格
setting redundant components in subsyste
setting redundant components in subsyste
练习题库
2022-08-02
52
问题
setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this? ( ) .A.risk avoidance B.risk acceptance C.risk mitigation D.contingency plan
选项
A.risk avoidance
B.risk acceptance
C.risk mitigation
D.contingency plan
答案
C
解析
翻译:为子系统设置冗余组件处理原系统带来的风险,是一种什么样的风险应对策略?A.风险规避 B.风险接受C.风险减轻 D.应急计划冗余减少了风险发生概率,属于风险减轻。
转载请注明原文地址:http://tihaiku.com/congyezige/2295942.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
settingredundantcomponentsinsubsyste
settingredundantcomponentsinsubsyste
随机试题
(1)LarrySummersisright;thisyear’sFedsymposiuminJacksonHolewastri
Thebiggestsafetythreatfacingairlinestodaymaynotbeaterroristwith
[originaltext]W:Goodmorning,class.TodayIthoughtwewouldtalkaboutsomet
[originaltext]Youmaynotrealizethatfogissimplyacloudthattouchest
处于从没有任何心理紊乱到患有精神疾病之间的过渡带中的人们,是()A.心理咨询的对
男,13岁,因全身发绀和突然意识丧失半小时入院。患儿于生后8个月发现双眼睑下垂,
下列施工组织设计技术经济分析指标中,不属于机械指标的是( )。A.施工机械化程度
小明是当天值日生,没有完成打扫任务,放学就直接走了,你怎么办?
良好的医患沟通有利于建立融洽的医患关系,其目的不包括:()。A.使医患形成
在计算机中采用二进制,是因为:A.可降低硬件成本 B.两个状态的系统具有稳
最新回复
(
0
)