某项目的现金流量图如下图所示。若该项目基准收益率为i,则净现值为()A:-A0+

资格题库2022-08-02  30

问题 某项目的现金流量图如下图所示。若该项目基准收益率为i,则净现值为()A:-A<sub>0</sub>+A<sub>4</sub>(P/F,i,4)+A<sub>5-8</sub>(P/A,i,8)+A<sub>9</sub>(P/F,i,9)B:-A<sub>0</sub>+A<sub>4</sub>(P/F,i,4)+A<sub>5-8</sub>(P/A,i,8)(P/F,i,4)+A<sub>9</sub>(P/F,i,9)C:-A<sub>0</sub>+A<sub>4</sub>(P/F,i,4)+A<sub>5-8</sub>(P/A,i,4)(P/F,i,4)+A<sub>9</sub>(P/F,i,9)D:-A<sub>0</sub>+A<sub>4</sub>(P/F,i,4)+A<sub>5-8</sub>(P/A,i,4)(P/F,i,5)+A<sub>9</sub>(P/F,i,9)

选项 A:-A0+A4(P/F,i,4)+A5-8(P/A,i,8)+A9(P/F,i,9)
B:-A0+A4(P/F,i,4)+A5-8(P/A,i,8)(P/F,i,4)+A9(P/F,i,9)
C:-A0+A4(P/F,i,4)+A5-8(P/A,i,4)(P/F,i,4)+A9(P/F,i,9)
D:-A0+A4(P/F,i,4)+A5-8(P/A,i,4)(P/F,i,5)+A9(P/F,i,9)

答案 C

解析 净现值是将项目整个计算期内各年的净现金流量按某个给定的折现率,折算到计算期期初(零点,也即1年初)的现值代数和。
转载请注明原文地址:https://tihaiku.com/jzgc/342015.html

最新回复(0)