The perform Integrated Change Contorl pr
The perform Integrated Change Contorl pr
考试题库
2022-08-02
69
问题
The perform Integrated Change Contorl process is the ultimate responsibility of the().Although changes may be initiated verbally,they should be recorded in written form and entered into the()system.问题1选项A.resource managerB.division managerC.functional managerD.project manager问题2选项A.quality managementB.configuration managementC.risk managementD.scope management
选项
答案
DB
解析
执行综合变更控制程序是项目经理的最终责任。虽然变更可以口头启动,但应以书面形式记录并输入配置管理系统。
转载请注明原文地址:https://tihaiku.com/congyezige/2412610.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
TherearedifferentwaystoperformIPb
Qualitycontrolisnormallyperformedby
Performing( )involvesmonitoringspeci
TheperformIntegratedChangeContorlpr
WhenrequiredtheperformIntegratedCha
随机试题
[originaltext]M:Today,weinviteMs.Lesleytotalkabouteducation.Howd
Whensheheardthebadnews,hereyes______withtearsasshestruggledtocontro
关于脑发育的描述,正确的是A.最早发育 B.3岁时接近成人脑重 C.生后脑重
详细的项目范围说明书是指导项目成功实施的关键文件。()不应该属于范围定义的输入
垂体微腺瘤是指肿瘤直径A.<1cm B.>3cm C.<2cm D.>4c
A.胆道出血 B.胃癌 C.门脉高压症 D.应激性溃疡 E.胃、十二指肠
2015年,张先生在国家扩大内需政策的鼓舞下,购买了一辆价值10万元的小轿车。深
在厂部和车间可分别成立定额修订领导小组,吸收()参加修订。A.计划部门有关人员
下列立井施工采用吊桶提升的安全要求,说法正确的是()。A.吊桶上的关键部件,每班
腹股沟深环位于( )。A.腹股沟中点上方1cm B.腹股沟中点上方2cm
最新回复
(
0
)