The perform Integrated Change Contorl pr

考试题库2022-08-02  38

问题 The perform Integrated Change Contorl process is the ultimate responsibility of the().Although changes may be initiated verbally,they should be recorded in written form and entered into the()system.问题1选项A.resource managerB.division managerC.functional managerD.project manager问题2选项A.quality managementB.configuration managementC.risk managementD.scope management

选项

答案 DB

解析 执行综合变更控制程序是项目经理的最终责任。虽然变更可以口头启动,但应以书面形式记录并输入配置管理系统。
转载请注明原文地址:https://tihaiku.com/congyezige/2412610.html

最新回复(0)