首页
登录
从业资格
During planning you sit down and estimat
During planning you sit down and estimat
题库
2022-08-02
41
问题
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario ( ) .A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate;should be the same as the customer's reqhired completion date
选项
A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate;should be the same as the customer's reqhired completion date
答案
B
解析
当你计划坐下来,估计每个任务所需的时间和总他们的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是
B选项:团队不需要创建估算,不需要用到网络图
转载请注明原文地址:https://tihaiku.com/congyezige/2412589.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
企业系统规划(BusinessSystemPlanning,BSP)的实现步
Workaroundsaredeterminedduringwhich
Onetoolthatisusefulduringbothanal
Duringplanningyousitdownandestimat
Duringtheinstallationofthegroove,t
Duringtheimplementationoftheproject
Duringtheinstallationofthegroove,th
()Estimatingcurrentprojectcostsbya
Duringtheimplementationoftheproject
随机试题
Todefinesciencewemaysimplycallit______.[br]Ascientistbeingintereste
DaydreamingⅠ.Daydreamingcanbeharmfulbecauseitwascon
[originaltext]F:HeyKirk,weaxegettingawayfortheweekendtogocanoeing.
[originaltext]W:Iwanttoregisterforthismathematicscourse.M:I’msorryr
如果要将目标网络为202.117.112.0/24的分组经102.217.115
河北省2010年全年城镇居民人均可支配收入达16263.4元,比上年增长10.
大体积混凝土施工应选用下列中的哪种水泥?A.硅酸盐水泥 B.矿渣水泥 C.铝
有宫缩乏力的产妇应在胎儿什么部位娩出后立即肌内注射缩宫素10U,并继续静脉滴注缩
A.阿司匹林B.对乙酰氨基酚C.吲哚美辛D.吡罗昔康E.丙磺舒与三氯化铁试液作用
下列现金收支管理措施中,能提高现金利用效率的是( )。 A.充分使用现金浮
最新回复
(
0
)