首页
登录
从业资格
During planning you sit down and estimat
During planning you sit down and estimat
题库
2022-08-02
51
问题
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario ( ) .A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate;should be the same as the customer's reqhired completion date
选项
A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate;should be the same as the customer's reqhired completion date
答案
B
解析
当你计划坐下来,估计每个任务所需的时间和总他们的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是
B选项:团队不需要创建估算,不需要用到网络图
转载请注明原文地址:https://tihaiku.com/congyezige/2412589.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
企业系统规划(BusinessSystemPlanning,BSP)的实现步
Workaroundsaredeterminedduringwhich
Onetoolthatisusefulduringbothanal
Duringplanningyousitdownandestimat
Duringtheinstallationofthegroove,t
Duringtheimplementationoftheproject
Duringtheinstallationofthegroove,th
()Estimatingcurrentprojectcostsbya
Duringtheimplementationoftheproject
随机试题
Whenyoustartyournewjob,it’sagoodideatolookathowpeoplecommunicate
______(尽管我很崇拜他是个作家),Idon’tlikehimasaman.MuchasIadmirehimasawriter本
Doesbrainpower______aswegetolder?Scientistsnowhavesomesurprisinganswe
粪便中粪胆原含量明显增加主要见于A.胆道完全梗阻 B.肝细胞性黄疸 C.胆管
混凝土表面局部缺浆、粗糙,或有大量小凹坑的现象称为()。A:蜂窝 B:麻面
A.罕见的不良反应 B.所有可疑不良反应 C.A类药物不良反应 D.新的不
患者,男,37岁。每天都在想是先有蛋还是先有鸡,自己是从哪来,死后将要到哪里去。
团队有效性要素的构成不包括()A:团队学习 B:绩效 C:成员满意度
男孩,2岁。因颜面及四肢凹陷性水肿1周来诊。查体:BP85/55mmHg,尿蛋
建设用地使用权人将建设用地使用权转让、互换、出资、赠与或者抵押时,应当符合的规定
最新回复
(
0
)