首页
登录
从业资格
During planning you sit down and estimat
During planning you sit down and estimat
题库
2022-08-02
48
问题
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario ( ) .A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate;should be the same as the customer's reqhired completion date
选项
A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate;should be the same as the customer's reqhired completion date
答案
B
解析
当你计划坐下来,估计每个任务所需的时间和总他们的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是
B选项:团队不需要创建估算,不需要用到网络图
转载请注明原文地址:https://tihaiku.com/congyezige/2412589.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
企业系统规划(BusinessSystemPlanning,BSP)的实现步
Workaroundsaredeterminedduringwhich
Onetoolthatisusefulduringbothanal
Duringplanningyousitdownandestimat
Duringtheinstallationofthegroove,t
Duringtheimplementationoftheproject
Duringtheinstallationofthegroove,th
()Estimatingcurrentprojectcostsbya
Duringtheimplementationoftheproject
随机试题
DeniseSimmonsreceivedaburstofnationalattentionwhenshebecamemayor
[originaltext]W:Hello,Patrick,isthatyou?M:YeahJane,whatcanIdofory
PlantandAnimalLifeofthePacificIslandsP1:ThePacificIslandsregioncove
坍落度法适合测量坍落度在10mm以上任何值的混凝土的流动性。()
宫口开大9cm,阴道检查小囟位于5点钟方向,胎方位是A.枕左后位 B.枕左横位
可交换债券和可转换债券的不同之处有()。 ①发行主体不同②转股的股份来源不
各句划线的部分在修辞上与其他不同的一项是:A.“磨刀不误砍柴工”,花在度假上的时
某公司正在招聘管理人员,如果应聘人员有7年以上相关经验,或有研究生学历,就能够进
与速发型超敏反应无关的生物活性物质为A.白三烯 B.血小板活化因子 C.干扰
和电信管制相比,邮政管制特有的内容是()。A.服务质量管制 B.市场准入管制
最新回复
(
0
)