During planning you sit down and estimat

题库2022-08-02  48

问题 During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario (  ) .A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate;should be the same as the customer's reqhired completion date

选项 A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate;should be the same as the customer's reqhired completion date

答案 B

解析 当你计划坐下来,估计每个任务所需的时间和总他们的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是
B选项:团队不需要创建估算,不需要用到网络图
转载请注明原文地址:https://tihaiku.com/congyezige/2412589.html

最新回复(0)