Project manager believes that modifying

免费题库2022-08-02  19

问题 Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( )A.change the scope baselineB.contact the customer to determine if the change adds valueC.call A.meeting of the change control boardD.change the project's objectives

选项 A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call A.meeting of the change control board
D.change the project's objectives

答案 C

解析 项目经理认为修改项目范围可以为客户提供增值服务。项目经理应该通知项目变更控制委员会召开会议。
转载请注明原文地址:https://tihaiku.com/congyezige/2299667.html