Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( )A.change the scope baselineB.contact the customer to determine if the change adds valueC.call A.meeting of the change control boardD.change the project's objectives
选项
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call A.meeting of the change control board
D.change the project's objectives
答案
C
解析
项目经理认为修改项目范围可以为客户提供增值服务。项目经理应该通知项目变更控制委员会召开会议。
转载请注明原文地址:https://tihaiku.com/congyezige/2299667.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Ascheduleiscommonlyusedinprojectp
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Theprojectscheduleismorethanadocu
( )describes,indetail,theproject’
随机试题
【B1】[br]【B4】A、moonB、earthC、starBItmovedaroundtheearthfourteentimes.神州
ManyAmericansmindlesslyopposehunting.Theydosoevenincaseswhereani
[originaltext]Goodafternoon,everyone.Today,I’lltalkabouthowautonomo
A.从生物和社会结合上理解人的疾病和健康 B.不仅关心患者的躯体,而且关心病人
癃闭概念
几乎每个人都相信,自己的潜在价值没有完全发挥出来,如果充分实现了自我,那么他肯定
一种基金,对股票的配置比例在50%~70%,债券的配置比例在20%~40%,则这
下列各项活动中,通常被视为管理层职责的有()。A.确定采纳会计师事务所或其他第
共用题干 2013年4月,甲公司发生如下业务:(1)甲企业开出一张付款期限为3
35kV及以下输电线路一般不采取全线路架设避雷线措施的原因是( )。A.感应
最新回复
(
0
)