问题 Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider (  ).A、crashing the ScheduleB、performing resource levelingC、conducting reverse resource allocation SchedulingD、utilizing the critical chair resources

选项 A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources

答案 A

解析 由于团队成员之间的冲突,造成项目落后于进度计划,为了解决冲突以使得项目如期完成,你应该考虑:
A.重新安排时间表
B.实行资源调配
C.执行逆向资源分配调度
D.利用关键的主要资源