() is the process of obtaining the stake
() is the process of obtaining the stake
练习题库
2022-08-02
58
问题
() is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily.A.Project acceptance B.Scope verification C.Scope definition D.WBS Creation
选项
A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation
答案
B
解析
范围验证是指获得项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。
转载请注明原文地址:https://tihaiku.com/congyezige/2295905.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )istheprocessofimplementingrisk
( )isaprocessofdevelopingadetail
PlanQualityistheprocessofidentifyi
PerformQualityControlistheprocesso
Validatescopeistheprocessofformali
Agoalofthe()processistodetermin
Integration()istheprocessofverify
The()processanalyzestheeffectofrisk
Agoalofthe()processistodetermin
PlanQualityistheprocessofidentifyi
随机试题
WhatdoestheGoGroupdo?[br][originaltext]Hello,everyone,mytopictod
Tell-AllGenerationLearnstoKeepThingsOfflineMinLiu,a21-
试述苯二氮革类的药理作用及其作用机制。
如图所示,用一附有水压差计的毕托管测定某风道中空气流速。已知压差计的读数Δh=
下列选项中,可以假释的是A.累犯 B.毒品犯罪的再犯 C.强奸被判处10年有
MTX可抑制核苷酸代谢中的环节是A.UTP→CTP B.dUMP→dTMP
资产风险管理模式强调商业银行最经常性的风险来自()。A.资产业务 B.负
加涅将学习结果分为五类,并把它们看作是五种学习类型,它们分别是智慧技能、(
2014年第一季度我国经济开局平稳,中国人民银行根据国际收支和流动性供需形势,合
A. B. C. D.
最新回复
(
0
)