() is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily.A.Project acceptance B.Scope verification C.Scope definition D.WBS Creation
选项
A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation
答案
B
解析
范围验证是指获得项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。
转载请注明原文地址:https://tihaiku.com/congyezige/2295905.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )istheprocessofimplementingrisk
( )isaprocessofdevelopingadetail
PlanQualityistheprocessofidentifyi
PerformQualityControlistheprocesso
Validatescopeistheprocessofformali
Agoalofthe()processistodetermin
Integration()istheprocessofverify
The()processanalyzestheeffectofrisk
Agoalofthe()processistodetermin
PlanQualityistheprocessofidentifyi
随机试题
下面你将听到一段有关“中国文化年”的对话。//A:Bravo!ThoughIknowlittleaboutthebackgroundoft
TipsforThoseWhoTravelAloneA)Whenitcomestotraveling,sometimes
Don’tworry.You’llsoon______yourshyness.A、getoffB、getacrossC、getdownD、g
I’dratheryoumakeanycommentontheissueforthetimebeing.A、don’tB、w
带传动中,带离心力产生的拉应力,分布在带()。A.做圆周运动的部分 B.整
产生溶血素和透明质酸酶,感染易于扩散而缺乏局限化趋势A、溶血性链球菌 B、金黄
物业服务企业在进行市场定位时,关键在于确定合适的()。A:物业类型B:发展目标
资料:Specialneedsstudentscannotonlyl
两年前,某企业还没有专门的人力资源部门,人力资源的相关业务由当时的综合办公室承担
背景资料 A施工单位承建某新建单线铁路隧道,隧道全长1280m。根据设计图纸,
最新回复
(
0
)