首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
70
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:http://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Whatwillthewomando?[originaltext]21.M:Wouldyouliketocomeoutfor
DothefollowingstatementsagreewiththeinformationgiveninReadingPassage
Atwenty-year-oldimmigrant,LeviStrauss,cametotheUnitedStatesin185
TheUnitedStatestakesabiggershareoftheinternationalstudentmarkett
50milessouthwestofthecountry______thefamousbeautifulmountain.A、layingB、
Avacation-crushingtheoryonhowtoimprovestudentperformanceisgaining
在施工过程中,该工程所在地连续下了6天特大暴雨(超过了当地近10年来季节
温经汤中配伍半夏的主要用意是A.和胃降逆而止呕 B.通降胃气而散结 C.降逆
根据下图回答: 1999年至2003年广播电视行业六家上市公司主营收入图
工程测量应遵循( )的原则。A.由局部到整体,先控制后细部 B.由局部到整体,
最新回复
(
0
)