The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:http://tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Heobviouslystandsagoodchanceofgettingthepost,asheiswell______themo
Ithasalwaysbeendifficultforthephilosopherorscientiststofittimein
[originaltext]M:Weseemtobehavingthisconversationoverandoveragain.W:
给家兔静脉注射25%葡萄糖10ml后尿量增加,其原因是()A.抗利尿激素分泌
如果出血时间(BT)和血小板计数均正常,除了可以出现在正常人以外,可能见于A.血
混凝土配合比设计正确的顺序为()。①提出基准配合比。②确定试验室配合比。③
男性,60岁,胃病史8年,近3个月上腹痛,伴有食欲缺乏及体重下降胃镜下可见黏膜苍
善去脾胃大肠湿热,为治湿热泻痢要药的是A.黄芩 B.葛根 C.黄柏 D.苦
额定转速为1450r/min的三相异步电动机,空载运行时转差率为:
国境卫生检疫机关对来自疫区的、被检疫传染病污染的或者可能成为橙疫传染病传播媒介的
最新回复
(
0
)